PNC Park Stadium Coating Removal

PNC Park Stadium Coating Removal

PNC Park Stadium Coating Removal

  • Rampart removed approximately 27,000 SF of concrete coating, along with joint material, using our hand-held hydrodemolition lances.
  • Completed on time and under budget
  • No OSHA recordable incidents
Location
Pittsburgh, PA
Project Team
  • Owner:
    Sports & Exhibition Authority of Pittsburgh and Allegheny County

  • General Contractor:
    Concrete Preservation Systems
  • Coating Removal:
    Rampart Hydro

PNC Park is the home to the Pittsburgh Pirates, a major league baseball team. The stadium opened in March 2001 and has a seating capacity of approximately 38,000. After approximately 10 years, the concrete coatings in various sections required removal and replacement due to deterioration.

Rampart removed approximately 27,000 SF of concrete coating, along with joint material, using our hand-held hydrodemolition lances. This project was completed on time and under budget with no OSHA recordable incidents.